(Reuters) - U.S. energy firm Equitrans Midstream delayed the completion date for its Mountain Valley natural gas pipeline from West Virginia to Virginia to the second quarter of 2024 from the previous estimate of the first quarter.
The company also boosted the projected cost to complete the project to around $7.57 billion-$7.63 billion, up from a prior estimate of about $7.2 billion.
Equitrans spoke about Mountain Valley in its fourth earnings report, which beat estimates.
Mountain Valley is the only big gas pipeline under construction in the U.S. Northeast. It has encountered numerous regulatory and court fights that have stopped work several times since construction began in 2018.
The pipe, which is key to unlocking gas supplies from Appalachia, the nation's biggest shale gas-producing region, needed a bill from the U.S. Congress that was signed into law by the president and help from the Supreme Court before it could restart construction.
Related News
Related News
- Credit Agricole says it will not fund two major LNG projects
- Aramco awards $7.7-B contracts to add 1.5 Bscfd of raw gas to Fadhili Gas Plant
- Japan's JERA suspends output at 4 gas-fired power plants to secure LNG stocks
- Shareholders’ Resolution: MOL to pay $668-MM dividend
- TotalEnergies: Papua LNG project requires 'more work' to reach final investment decision
- Technip Energies awarded a major LNG contract for the North Field South Project by QatarEnergy
- Shell publishes Energy Transition Strategy 2024
- QatarEnergy to charter 19 new LNG vessels expanding fleet further
- Aramco awards $7.7-B contracts to add 1.5 Bscfd of raw gas to Fadhili Gas Plant
- Mabanaft announces successful acquisition of WESTFA Energy GmbH
Comments