Alexandroupolis LNG terminal to restart soon and hit capacity by September
The Alexandroupolis LNG terminal in Greece will begin a gradual restart soon and reach full capacity by September, the vice president and managing director of the operator Gastrade said.
Gastrade halted operations at Alexandroupolis in late January, citing technical issues at the 4.3 MMtpy terminal.
"By mid-September we should be 100% back on our capacity. That will happen gradually, probably starting at some point in May," Konstantinos Sifnaios told Reuters on the sidelines of the Budapest LNG Conference.
Two trading sources said that the technical issues were related to problems with booster pumps, used to ramp up the pressure of LNG when it comes from the tanks to enter regas trains.
Greece has boosted LNG imports to replace some of its Russian pipeline gas, which accounted for about 40% of its gas needs.
Related News
Related News
- Digital Exclusive: Evolving pressure relief valve designs protect LNG facilities
- JGC-Hyundai JV awarded EPC contract for major low-carbon LNG plant project in Papua New Guinea
- TC Energy approves $1.5-B Columbia Gas expansion after profit tops estimates
- NextDecade to use Honeywell liquefaction technology for 30-MMtpy LNG terminal
- Wärtsilä continues to expand its data center footprint with new 790 MW order in Texas

Comments