New Fortress Energy to deliver first LNG cargo from Altamira, Mexico plant in July
6/17/2024
New Fortress Energy (NFE) announced first LNG in the coming days and first cargo in July.
NFE today updated the timing of its First LNG expectation for its first Fast LNG unit located offshore Altamira, Mexico. New Fortress Energy has made tremendous progress on its path towards the start of liquefaction operations.
As of today, the work necessary to begin operations is complete and NFE has also completed the full remainder of pre-commissioning activities. The company now expects to produce LNG in the next 10 days, and then expects to be able to deliver its first cargo in July.
Related News
Related News
Sign up to Receive Our Newsletter
- Standard Charter delivers $15-B financing for Venture Global's CP2 LNG project
- Panama Canal engages industry players for the development of a natural gas pipeline
- Digital Exclusive: Carbon critical—How filtration adds value in CCUS systems
- Sempra sells $10-B infrastructure stake, greenlights Port Arthur LNG Phase 2
- 236-mile Texas-to-Gulf pipeline reaches FID in $2.3-B LNG expansion push

Comments