Cheniere produces first LNG at Corpus Christi Stage 3 project
Cheniere Energy on Monday said that liquefied natural gas (LNG) was produced for the first time from the first train (Train 1) of its Corpus Christi Stage 3 Liquefaction Project.
As the commissioning process continues, the company says it expects substantial completion of Train 1 to be achieved at the end of the first quarter of 2025.
As of Nov. 30, the overall project completion for the Corpus Christi Stage 3 was 75.9%, the Houston, Texas-based company said in a statement.
Upon completion, construction firm Bechtel Energy will hand over the care, control, and custody of the completed train to Cheniere, the company added.
The Corpus Christi Stage 3 Liquefaction Project consists of seven midscale trains and is projected to produce > 10 metric MMtpy of LNG. When these are substantially completed, the Corpus Christi liquefaction facility's capacity is expected to exceed 25 MMtpy of LNG.
Cheniere is the largest U.S. LNG exporter and the world's second largest producer of the superchilled gas. The company has played a key role in helping the U.S. become the world's largest exporter of LNG.
Related News
Related News
- Digital Exclusive: Evolving pressure relief valve designs protect LNG facilities
- JGC-Hyundai JV awarded EPC contract for major low-carbon LNG plant project in Papua New Guinea
- TC Energy approves $1.5-B Columbia Gas expansion after profit tops estimates
- NextDecade to use Honeywell liquefaction technology for 30-MMtpy LNG terminal
- Wärtsilä continues to expand its data center footprint with new 790 MW order in Texas

Comments