Sempra wins extension on Texas LNG project
The Federal Energy Regulatory Commission granted Sempra Energy an extension to build two pipelines in Texas and Louisiana to connect to a Texas LNG plant, and NextDecade is also seeking more time to build a Texas LNG project.
Sempra Energy was granted an extension until March 31, 2023, for the two pipelines that will connect to its Port Arthur LNG plant. NextDecade on Wednesday also sought an extension, to November 2028, for its Rio Grande LNG project in Brownsville, Texas.
NextDecade did not reply to a request for comment.
NextDecade also announced it had reached a 20-year deal to supply 1.5 MMtpy of LNG from the proposed Rio Grande facility to a unit of China's ENN Natural Gas Co.
Several LNG developers have announced new deals this year that could push ahead proposed plants. Energy Transfer signed a 2.7 MMtpy deal with ENN while Mexico Pacific Ltd received a 2 MMtpy deal from Chinese gas and power supplier Guangzhou Development Co.
In January, NextDecade said a financial investment decision for the Rio Grande LNG project would be delayed until the second half of the year. It was originally expected to start producing LNG in 2023.
At the start of 2020 and again in 2021, roughly a dozen firms signaled plans for financial investment decisions on proposed projects. But only Sempra's Costa Azul in Mexico started construction in 2020. Numerous others have been pushed into 2022.
(Reporting by Marcy de Luna; Editing by Kirsten Donovan and Leslie Adler)
- Digital Exclusive: Evolving pressure relief valve designs protect LNG facilities
- JGC-Hyundai JV awarded EPC contract for major low-carbon LNG plant project in Papua New Guinea
- TC Energy approves $1.5-B Columbia Gas expansion after profit tops estimates
- NextDecade to use Honeywell liquefaction technology for 30-MMtpy LNG terminal
- Wärtsilä continues to expand its data center footprint with new 790 MW order in Texas

Comments