Chevron to shut Australia Gorgon Train 3 for weld inspection, maintenance in second quarter
Chevron Corp plans to shut Train 3 at the Gorgon LNG plant off Western Australia in the second quarter for maintenance and weld inspections, the company said overnight.
The weld inspections are needed after problems were discovered in propane kettles in Trains 1 and 2 at the three-train, 15.6 million tonnes a year plant, which accounts for nearly 5% of global LNG trade.
In the second quarter he said the company needs to do inspections on Train 3 and any required repairs, then do a scheduled maintenance turnaround.
“We’ve actually increased the initial capacity by 5% and that incremental 5% is pretty valuable for us. And so we look forward to getting through the second quarter and establishing a good run of production as we enter the second half of this year,” Johnson said.
He said the company’s Wheatstone LNG plant is also operating back at full tilt, running 9% above its original design capacity of 8.9 million tonnes a year, after repairing equipment that separates natural gas and associated liquids at its Wheatstone offshore processing platform.
Reporting by Sonali Paul; editing by Richard Pullin
- Digital Exclusive: Evolving pressure relief valve designs protect LNG facilities
- JGC-Hyundai JV awarded EPC contract for major low-carbon LNG plant project in Papua New Guinea
- TC Energy approves $1.5-B Columbia Gas expansion after profit tops estimates
- NextDecade to use Honeywell liquefaction technology for 30-MMtpy LNG terminal
- Wärtsilä continues to expand its data center footprint with new 790 MW order in Texas

Comments