Pennsylvania orders Sunoco to reroute section of Mariner East 2 NGL pipe
Pennsylvania environmental regulators ordered Energy Transfer LP's Sunoco Pipeline unit to reroute a section of the Mariner East 2 NGL pipeline after spilling 8,000 gallons of drilling fluid in Marsh Creek State Park.
Analysts at Height Capital Markets said the reroute could delay an upgrade to the already operating Mariner East 2 project that was expected to be completed in the second quarter of 2021.
Officials at Energy Transfer were not immediately available for comment.
The Pennsylvania Department of Environmental Protection said the Marsh Creek spill caused the park to close 33 acres (13 hectares) of the lake from boating and other recreational uses.
"These incidents are yet another instance where Sunoco has blatantly disregarded the citizens and resources of Chester County with careless actions while installing the Mariner East II Pipeline," DEP Secretary Patrick McDonnell said in a statement.
The reroute order was the latest in a long series of sanctions against the company for violations of its permits during construction of Mariner East 2.
Since May 2017, Pennsylvania has issued 115 notices of violation to Mariner East, mostly for drilling fluid spills, including one in September.
Pennsylvania has fined the company and stopped construction on the pipe several times. Several politicians and local groups have long urged the state to stop work again and shut the pipe.
Mariner East transports liquids from the Marcellus and Utica shale in western Pennsylvania to customers in the state and elsewhere, including international exports from Energy Transfer's Marcus Hook complex near Philadelphia.
Sunoco started work on the $2.5 billion Mariner East expansion in February 2017 and had planned to finish the 350-mile (563-km) pipeline in the third quarter of 2017.
But completion was delayed until December 2018 due to several work stoppages by state agencies.
(Reporting by Scott DiSavino; editing by Jonathan Oatis)
- Digital Exclusive: Evolving pressure relief valve designs protect LNG facilities
- JGC-Hyundai JV awarded EPC contract for major low-carbon LNG plant project in Papua New Guinea
- TC Energy approves $1.5-B Columbia Gas expansion after profit tops estimates
- NextDecade to use Honeywell liquefaction technology for 30-MMtpy LNG terminal
- Wärtsilä continues to expand its data center footprint with new 790 MW order in Texas

Comments