Destin Pipeline to reroute shippers impacted by force majeure
6/30/2016
(Reuters) Destin Pipeline aims to provide natural gas shippers impacted by a pipeline force majeure access to the VKGS delivery point by Wednesday evening, pending successful testing of meters and good weather, the company said in a notice on Wednesday.
Total re-routed gas flows into the VKGS delivery point will be limited to 350 MMcfd, the notice said.
Destin Pipeline declared force majeure and stopped shipments from offshore receipt points on Tuesday following a fire at Enterprise Product Partners' (EPP) natural gas processing plant in Pascagoula, Mississippi.
EPP has not yet indicated when it expects the plant to resume operations, Destin said in the notice.
Reporting by Liz Hampton
Sign up to Receive Our Newsletter
- Cheniere signs deal with Bechtel to expand U.S. LNG export capacity
- TC Energy approves $1.5-B Columbia Gas expansion after profit tops estimates
- Baker Hughes’ fuel flexible NovaLT™ 16 gas turbine certified by RINA for marine propulsion
- Commonwealth LNG FID attracts global syndicate of leading banks
- Dozens injured, 18 missing after blast during restart at giant Qatar LNG site

Comments