Chevron to resume exports from Gorgon LNG plant
6/27/2016

After more than three months of downtime, the Barrow Island LNG plant has begun startup activities and will resume LNG production soon, according to a Chevron Australia spokesperson. The plant shut down due to a technical fault after shipping its first cargo on March 21.
Five cargoes are expected to ship in July. The first of these is expected to ship on July 1 via the Marib Spirit tanker.
Initially, gas exports were to begin near the end of 2014, but the project has suffered from multiple setbacks, including a construction delay of almost 18 months. Delays from the recent technical fault have also surpassed the original 30-60 day estimate by Chevron.
Sign up to Receive Our Newsletter
- Cheniere signs deal with Bechtel to expand U.S. LNG export capacity
- TC Energy approves $1.5-B Columbia Gas expansion after profit tops estimates
- Baker Hughes’ fuel flexible NovaLT™ 16 gas turbine certified by RINA for marine propulsion
- Commonwealth LNG FID attracts global syndicate of leading banks
- Dozens injured, 18 missing after blast during restart at giant Qatar LNG site

Comments