Shell enters two-month turnaround on Pearl GTL train in Qatar
Shell said today that its Pearl gas-to-liquids (GTL) plant in Qatar entered planned maintenance in February 2015.
Pearl GTL comprises two identical GTL ‘trains’, with a total capacity of 140,000 bpd of GTL products plus 120,000 bpd of natural gas liquids and ethane.
One train, representing half the facility, has recently begun a planned ‘turnaround’ maintenance program, which will continue for a period of some two months.
The Pearl GTL project was developed in two phases. The first phase started up in early 2011 and exported the first commercial shipment of gasoil in June 2011. The whole plant ramped up to full production at the end of 2012.
The plant produces cleaner-burning diesel and aviation fuel, oils for advanced lubricants, naphtha used to make plastics and paraffin for detergents.
It makes enough diesel to fill over 160,000 cars/day and enough synthetic oil each year to make lubricants for more than 225 million cars.
The products reach customers in every major energy market through Shell’s global retail network.
- Mitsubishi Heavy Industries Compressor acquires Swiss rotating equipment maintenance company AST Turbo AG
- Digital Exclusive: Evolving pressure relief valve designs protect LNG facilities
- Qatar’s Ras Laffan LNG hub hit by missile attack, ‘extensive damage’ reported
- JGC-Hyundai JV awarded EPC contract for major low-carbon LNG plant project in Papua New Guinea
- Iran attacks wipe out 17% of Qatar’s LNG capacity for up to five years

Comments