Cheniere produces first LNG at Corpus Christi Stage 3 project
Cheniere Energy on Monday said that liquefied natural gas (LNG) was produced for the first time from the first train (Train 1) of its Corpus Christi Stage 3 Liquefaction Project.
As the commissioning process continues, the company says it expects substantial completion of Train 1 to be achieved at the end of the first quarter of 2025.
As of Nov. 30, the overall project completion for the Corpus Christi Stage 3 was 75.9%, the Houston, Texas-based company said in a statement.
Upon completion, construction firm Bechtel Energy will hand over the care, control, and custody of the completed train to Cheniere, the company added.
The Corpus Christi Stage 3 Liquefaction Project consists of seven midscale trains and is projected to produce > 10 metric MMtpy of LNG. When these are substantially completed, the Corpus Christi liquefaction facility's capacity is expected to exceed 25 MMtpy of LNG.
Cheniere is the largest U.S. LNG exporter and the world's second largest producer of the superchilled gas. The company has played a key role in helping the U.S. become the world's largest exporter of LNG.
Related News
Related News
- Freeport LNG export plant in Texas reports shutdown of liquefaction train
- TotalEnergies and Mozambique announce the full restart of the $20-B Mozambique LNG project
- RWE strengthens partnerships with ADNOC and Masdar to enhance energy security in Germany and Europe
- Five energy market trends to track in 2026, the year of the glut
- Venture Global wins LNG arbitration case brought by Spain's Repsol

Comments