bp's Tangguh LNG Train 3 resumes operations after week-long outage
2/22/2024
(Reuters)—The third train of bp's Tangguh liquefied natural gas (LNG) facility in West Papua, Indonesia has resumed operations after an outage of about a week, the country's upstream oil and gas regulator SKK Migas said on Wednesday.

"There was a problem with a broken component, but it has since been replaced," said SKK Migas spokesperson Hudi Suyodipuro, adding that the train resumed operations on Tuesday.
"Our focus now is to ensure that full capacity be reached soon to catch up on production."
The first cargo of LNG from the third train was shipped in October to a power plant operated by state utility firm Perusahaan Listrik Negara.
Train 3 would increase the Tangguh LNG facility's capacity by 3.8 MM metric tpy to 11.4 MM metric tpy.
Related News
Related News
Sign up to Receive Our Newsletter
- Mitsubishi Heavy Industries Compressor acquires Swiss rotating equipment maintenance company AST Turbo AG
- Digital Exclusive: Evolving pressure relief valve designs protect LNG facilities
- Qatar’s Ras Laffan LNG hub hit by missile attack, ‘extensive damage’ reported
- JGC-Hyundai JV awarded EPC contract for major low-carbon LNG plant project in Papua New Guinea
- Iran attacks wipe out 17% of Qatar’s LNG capacity for up to five years

Comments