Update: Kinder Morgan Elba LNG export plant in Georgia (U.S.) starts to take in natgas
U.S. energy firm Kinder Morgan's Elba Island liquefied natural gas export (LNG) plant in Georgia was on track to take in a small amount of natural gas on Friday, a sign it could be exiting a two-day maintenance outage, data from LSEG showed.
Data from the financial firm said the amount of gas flowing to Elba was less than 0.1 Bft3d on Friday, up from zero on Wednesday and Thursday. That compares with an average of 0.4 Bft3d over the prior seven days.
The scheduled maintenance at Elba Island was for a system upgrade, and the entire plant should be back up by the weekend, Kinder Morgan said on Friday.
Elba is capable of turning about 0.4 Bft3d of gas into LNG.
All of the LNG from Elba goes to British multinational oil and gas firm Shell under a long-term contract.
One Bft3 is enough to supply about 5 MM U.S. homes for a day.
Related News
Related News
- ExxonMobil halts 1-Bft3d blue hydrogen project in Texas
- 236-mile Texas-to-Gulf pipeline reaches FID in $2.3-B LNG expansion push
- Bechtel shares findings of tragic accident at Port Arthur LNG facility
- Aramco and Yokogawa commission multiple autonomous control AI agents at Fadhili gas plant
- Ukraine will resume gas imports via Transbalkan route in November

Comments