U.S. natgas flows to LNG export plants on track to hit 9-month high
The amount of gas flowing to the seven big operating U.S. liquefied natural gas (LNG) export plants was on track to rise to a nine-month high on Thursday as feedgas to a few plants hit multi-week highs, according to data from financial firm LSEG.
The energy market cares about feedgas flows to U.S. LNG plants because exports have been the gas industry's biggest source of demand growth in recent years.
The U.S. became the world's biggest LNG supplier in 2023, ahead of recent leaders Australia and Qatar, as much higher global prices, feed demand for more exports due in part to supply disruptions, and sanctions linked to Russia's invasion of Ukraine in February 2022.
U.S. LNG feedgas was on track to rise from 14.0 Bft3d on Wednesday to a nine-month high of 14.4 Bft3d on Thursday.
One Bft3 can supply about 5 MM U.S. homes for a day.
That increase in gas flows was due to rising feedgas at several plants.
Flows to Venture Global LNG's 1.6-Bft3d Calcasieu Pass in Louisiana were on track to rise to a four-month high of 1.5 Bft3d on Thursday.
Flows to Cameron LNG's 2-Bft3d Cameron plant in Louisiana were on track to rise to a four-week high of 2.3 Bft3d on Thursday.
Flows to Cheniere Energy's 4.5-Bft3d Sabine Pass in Louisiana were on track to rise to a three-week high of 4.9 Bft3d on Thursday. Sabine is the biggest U.S. LNG export plant.
LNG export plants can pull in more gas than they can turn into LNG because they use some of that fuel to run liquefaction and other equipment.
In addition to the operating export plants, the gas market is waiting for two new facilities under construction to enter service in test mode before the end of the year - the first 1.8-Bft3d phase of Venture Global's Plaquemines in Louisiana and the 1.5-Bft3d Stage 3 expansion at Cheniere's Corpus Christi in Texas.
Plaquemines has been pulling in small amounts of pipeline gas in test mode every day since mid-September, according to LSEG data. Many analysts expect the plant to start pulling in more gas in coming days or weeks to test the plant's liquefaction trains, which turn gas into LNG.
Related News
Related News
- Gasum selects Wärtsilä for another bio-LNG project in Sweden
- Linde selected to supply carbon capture technology to ADNOC’S Hail and Ghasha project
- Tecnimont to build waste-to-biogas plant to fuel local kitchens in India
- Topsoe, Aramco sign JDA to advance low-carbon hydrogen solutions using eREACT™
- Indonesia regulator confirms disruption at bp's Tangguh LNG project
Comments