Next wave of LNG supply delayed to 2027 due to project hold-ups, TotalEnergies says
The next wave of liquefied natural gas (LNG) supply will come online from 2027, later than the earlier forecast of 2025, due to project delays, TotalEnergies' Senior Vice President for LNG Gregory Joffroy said on Tuesday.
"On the mid-term (outlook), we see some LNG projects that were due to come onstream in the coming months have been delayed. The exact start date will impact the gas balances and supplies," Joffroy said at the Asia Gas Markets conference. "In the long term, it is clear that we will have a new supply wave by 2027 (through to) 2030."
In the U.S., a shortage of skilled labor, inflation from strong wage growth and equipment shortages have pressured LNG developers and delayed some projects there, while President Joe Biden's January pause on approvals for new LNG export projects has also created uncertainty.
Joffroy said he expects LNG demand to be higher in 2035 from current consumption levels, as utilities that are still consuming coal will switch to gas-fired power generation and with the development of renewables.
"With the development of renewables, people need a solution to resolve intermittency issues, and gas is a perfect solution."
Related News
Related News
- Japan's Mitsubishi to acquire stake in Petronas LNG plant
- McDermott awarded Rovuma LNG Phase 1 FEED contract in Mozambique
- Fincantieri LNG-powered Star Princess launched in Monfalcone
- Wood leads industry project to accelerate CCUS with guidelines for CO2 specifications
- Picarro launches handheld solution for natural gas leak investigation and closed-loop leak management
- Picarro launches handheld solution for natural gas leak investigation and closed-loop leak management
- Fincantieri LNG-powered Star Princess launched in Monfalcone
- Sonatrach, Saudi Aramco raise prices for LPG by 3%–4% in October
- Amarinth secures $1-MM order of API 610 pumps for Coral North FLNG project in Mozambique
Comments