Vietnam's first LNG power plant to start commercial operations from April 2025, five months behind target
Vietnam's first power plant using solely liquefied natural gas (LNG) is expected to start commercial operations from April next year, state media reported on Thursday, five months later than the previous target date.
A test run at the plant, Nhon Trach 3 in the southern province of Dong Nai, will begin in mid-October, reported Cong Thuong, a newspaper of the Ministry of Industry and Trade.
The nearby Nhon Trach 4 plant is expected to start commercial power generation in July 2025, the report said, two months behind schedule.
Both plants, which have a combined capacity of 1.5 gigawatts (GW), are being developed by PetroVietnam Power Corp. They are the first in a fleet of 13 LNG-fired plants with total capacity of 22.4 GW that Vietnam aims to have by 2030.
PetroVietnam Power said earlier this year that construction of the two plants had faced obstacles, including issues related to a power purchase agreement, land leases, and transmission lines from the plants.
Related News
Related News
- Gasum powers Equinor's platform supply vessel with bio-LNG
- ADNOC deploys pioneering AI-enabled process optimization technology
- Mexico Pacific announces long-term LNG SPA with POSCO International
- ONEOK to acquire Medallion and controlling interest in EnLink for $5.9 B
- Golar LNG signs EPC deal for $2.2-B MK II FLNG conversion project
- ONEOK to acquire Medallion and controlling interest in EnLink for $5.9 B
- Picarro launches handheld solution for natural gas leak investigation and closed-loop leak management
- Fincantieri LNG-powered Star Princess launched in Monfalcone
- Oman plans third LNG train, boosting domestic production to more than 15 MMtpy
- Brazil's fossil push undermines Lula's green ambitions
Comments