Repsol Polímeros in Sines, Portugal, scheduled an overhaul for two Process Gas Compressors (primary) and two F6 Hyper Compressors (secondary).
After two years of methodical preparation together with Burckhardt Compression, the planned turnaround date was suddenly moved forward by more than a month due to an unrelated equipment breakdown at the plant.
Burckhardt Compression rapidly responded to the changing circumstances and carried out the overhaul in a very tight fixed window to the customer’s full satisfaction.