Croatia extends LNG terminal gas bidding deadline
ZAGREB, (Reuters) - A deadline for bids on output from a planned offshore liquefied natural gas (LNG) terminal to be built on Croatia’s northern Adriatic island of Krk has been extended until Sept. 28, developers LNG Croatia said.
Demand will dictate the capacity of the 250 million euro terminal, which is part of EU-led efforts to diversify away from Russian energy imports.
The deadline on bidding for output was Aug. 3 but was delayed on requests from potential customers who are still in negotiations, LNG Croatia said.
The European Commission this week said it had earmarked 124 million euros for the project which will supply gas to countries in eastern and central Europe, regions which rely heavily on Russian gas.
Croatia’s parliament in June passed a law which cleared the way for construction of the terminal.
$1 = 0.8638 euros
Reporting by Maja Zuvela in Sarajevo; editing by Jason Neely
- ExxonMobil halts 1-Bft3d blue hydrogen project in Texas
- Aramco and Yokogawa commission multiple autonomous control AI agents at Fadhili gas plant
- Ukraine will resume gas imports via Transbalkan route in November
- Mitsubishi to inject $260 MM into Brunei LNG project
- Freeport LNG (U.S.) on track to take in more natgas on Thursday after unit outage

Comments