BP's Tangguh Train 2 LNG plant in Indonesia to shut for nearly 2 months
3/8/2017
JAKARTA (Reuters) -- Oil and gas giant BP will shut down its Tangguh Train 2 liquefied natural gas plant in Indonesia's West Papua province for nearly two months for maintenance, a company executive said on Wednesday.
Photo Courtesy of BP. |
The routine maintenance from early April to the third week of May has been factored into Tangguh's 2017 production plan this year, BP's Indonesia country head, Dharmawan Samsu, told Reuters.
The Tangguh Train 2 plant has an annual capacity of 3.8 MMt of LNG. The overall Tangguh project, which also includes Train 1, delivered a record of 119 LNG cargos last year.
Reporting by Wilda Asmarini; Writing by Eveline Danubrata, editing by David Evans
Sign up to Receive Our Newsletter
- Gasum powers Equinor's platform supply vessel with bio-LNG
- ADNOC deploys pioneering AI-enabled process optimization technology
- Mexico Pacific announces long-term LNG SPA with POSCO International
- ONEOK to acquire Medallion and controlling interest in EnLink for $5.9 B
- Golar LNG signs EPC deal for $2.2-B MK II FLNG conversion project
Comments